Do older Shasta County homes need an asbestos and lead survey before demolition

Pull the build date off the permit record before anyone books an excavator, because a house built before 1980 in Shasta County, CA is treated as suspect until a survey says otherwise. The breakdown sitting on demolition services shasta county razvan boar lists the usual hiding places in order, and the demolition schedule is built around the survey result, not the other way round.
What an asbestos survey actually samples

A surveyor takes small pieces of suspect material and sends them to a lab. The list is long: popcorn ceiling texture, joint compound on drywall, vinyl floor tile and its black mastic, roofing felt, duct wrap, and the cement board behind older tile. A house near Anderson built in the fifties can have all of those in one kitchen. Each material is sampled separately, because one clean sample says nothing about the next layer.
Where lead paint turns up

Lead sits in old paint on window trim, door casings, porch posts and exterior siding. It is tested with swabs or an XRF reading. When a stud wall is torn down the paint breaks into dust, and that dust settles in the soil around the footing. For that reason the soil next to an older foundation near Redding is sometimes sampled after the house is gone.
What happens when something tests positive
Abatement comes first. A licensed crew removes the affected material, bags and seals it, and takes it to a facility that accepts it. Demolition does not start until clearance paperwork is in hand. Skipping that order spreads fibers across the yard and over the property line, and it can stop a job halfway when an inspector arrives.
Why burned houses are surveyed too
Fire does not remove asbestos. It breaks the material up and mixes it into the ash. A pre-1980 house lost in the Carr Fire or a later burn near Shasta Lake is surveyed the same way, with extra care taken around the debris pile, which is kept wet and handled as suspect until the lab results come back.
Timing the survey
Lab results take days, not hours, and the notice to the air district has its own waiting period. The survey belongs at the very start of the job, ahead of the machine work. A concrete slab and footing do not carry asbestos, but the floor coverings sitting on top of them can, so the slab is surveyed with the rest of the house.